Construction progress of Dubai’s $3.2bn Azizi Riviera home hits 40%

English
29 أبريل 2019آخر تحديث : منذ 5 سنوات
Construction progress of Dubai’s $3.2bn Azizi Riviera home hits 40%

Azizi Riviera - مجلة مال واعمال

Azizi Riviera, the $3.2bn (AED12bn) waterfront residential project that Azizi Developments is building in Dubai’s Meydan One neighbourhood, has achieved an overall construction completion rate of 40%, officials from the real estate company told Construction Week.

Phase 1 of the development has noted 50% progress, followed by 35% completion of Phase 2.

Of the 71 buildings being constructed as part of Azizi Riviera, 18 are included in Phase 1, and 17 in Phase 2.

Phase 3 comprises 13 buildings, while the fourth stage features 22 structures. Two buildings each in the third and fourth phases are 22 floors high.

Executive director of engineering at Azizi Developments, Mohamed Ragheb Hussien, told Construction Week that the developer planned to deliver Phase 1 by Q4 2019.

Azizi Riviera includes 16,000 units, and each building ranges from seven to ten floors in height. Each floor comprises eight to 12 apartments.

KSS Engineering and Construction and Zahrat Al Safa Contracting are working on Phases 1 and 2 of the project. According to Hussein, both the first and second phases have a combined value of $1.7bn (AED6.2bn).

Prestige Construction is working on Phase 3 of Azizi Riviera under a $259m (AED952m) contract.

رابط مختصر

اترك تعليق

لن يتم نشر عنوان بريدك الإلكتروني.


شروط التعليق :

عدم الإساءة للكاتب أو للأشخاص أو للمقدسات أو مهاجمة الأديان أو الذات الالهية. والابتعاد عن التحريض الطائفي والعنصري والشتائم.